House extension under construction showing brick walls and timber roof frame
Planning & process · Timeline guide

How long does a house extension take?

A realistic stage-by-stage timeline from first idea to completion certificate — typical durations for every phase.

Updated June 2026Sourced from trade and government guidance
HE
House Extension Answers editorial
Reviewed against the Planning Portal, LABC building control, RICS and the Party Wall etc. Act 1996.

The short answer

On site, a single-storey extension typically takes 8–12 weeks; a double-storey takes 14–20 weeks. But the full journey from decision to completion — including design, planning and procurement — usually takes 6–12 months for a single-storey and 9–18 months for a double-storey. See planning permission and building regulations for the consent stages that add time.

One of the most common frustrations with extension projects is discovering that the build itself is the shortest part of the process. Design, planning consent and procurement can easily take as long as the construction stage, or longer. Setting realistic expectations at the outset — and building buffer time into your programme — reduces stress and avoids the common mistake of booking a builder before the planning decision has been made.

Extension timeline at a glance

Stage one: design (4–10 weeks)

The design stage starts when you appoint an architect or designer. They will measure up, discuss your brief, prepare initial concept designs, develop these into planning drawings and eventually produce detailed construction drawings for building regulations and the builder. For a single-storey PD extension, this can take as few as four to six weeks. For a project requiring full planning permission, the design needs to be more developed before submission, and the architect may need to resolve planning policy questions or consult the LPA informally before applying — allow six to ten weeks or more. See do I need an architect? for how to choose the right professional.

Stage two: planning and consents (6–16 weeks)

If your extension falls within permitted development, you may need only a prior approval application under the neighbour consultation scheme, which takes up to 42 days (about six weeks). If you need full planning permission, the LPA has an 8-week statutory target for householder applications (13 weeks for larger or more complex applications). In practice, processing times vary and some authorities run slower than their target, particularly for controversial applications or where further information is requested. If the application is refused and you appeal, add six to twelve months. This is the stage that most frequently causes programmes to slip.

Extension typeConsent typeTypical decision time
Single-storey (PD, under limits)Prior approval or none42 days or automatic
Single-storey (full planning)Householder application8–13 weeks
Double-storeyHouseholder application8–13 weeks (often longer)
Listed buildingListed building consent + planning8 weeks each (in parallel ideally)
Do not book a builder before the planning decision: if planning is refused, a redesign can delay the project by months. Line up your builder, agree a start date provisionally, and confirm only once the consent is in hand. Good builders are often booked 2–4 months out — manage this expectation early. See how to choose a builder for when to start procurement.

Stage three: procurement (2–6 weeks)

Once you have planning consent and construction drawings, you go out to builders for quotes. Getting at least three written quotes, evaluating them on a like-for-like basis, taking references, and negotiating a contract typically takes two to six weeks. Experienced extension builders in popular areas are often busy: you may need to wait two to four months for a start date. This is normal; it is not a sign that you should rush to the first builder who is available immediately. See how to choose a builder for an extension for the full procurement checklist.

Stage four: build (8–20 weeks on site)

The on-site build time depends primarily on the type and size of extension. A typical single-storey rear extension of 20–30 m² takes 8–12 weeks. A double-storey extension takes 14–20 weeks. Factors that extend the programme include:

Stage five: completion and sign-off (1–4 weeks)

The final building control inspection confirms compliance and the completion certificate is issued. This is the formal end of the regulatory process. Allow one to four weeks for snagging, final decorating and the builder completing outstanding items, plus the building control body’s processing time. Building control sign-off is not a formality: inspectors do occasionally require remedial work before issuing the certificate.

This page gives typical timelines for England. Programmes vary by LPA processing times, builder availability and project complexity. Always build contingency into your programme and discuss the realistic timeline with your architect and builder at the outset.

Start your extension project

Getting written quotes from experienced extension builders is the right step once you have a clear brief. No obligation.

Free to use. No obligation. We are an independent guide, not a builder.

Frequently asked questions

How long does planning permission take for an extension?

A householder planning application has an 8-week statutory determination target in England (13 weeks for larger applications). In practice some authorities take longer. Prior approval for PD extensions takes up to 42 days.

How long does it take to build a single-storey extension?

On site, typically 8–12 weeks for a standard single-storey rear or side extension. The full project from first meeting with an architect to receiving the completion certificate is usually 6–10 months.

Can a builder start before building regulations approval?

You can start after serving a building notice or submitting Full Plans (even before formal approval in some cases), but the inspector must be notified before work begins. Starting without any notification is a breach of the regulations.

What is the most common cause of extension delays?

Planning processing times and builder availability are the most common external delays. Client changes to specification mid-build are the most common internal cause. Plan carefully, finalise your design before work starts, and build programme contingency in from the start.

Sources & further reading

This is general information about house extensions in England and is not planning, structural, legal or financial advice. Costs, timescales and outcomes vary with your design, ground conditions, specification and local authority. Always obtain written quotes and verify planning and building regulations requirements with your local planning authority before committing to any works.